Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: SR 520 Floating Bridge Replacement
Location: Seattle, Washington
Year: 2018
Project Size: $4.4 billion
Scope: Replacement of floating highway bridge with enhanced seismic and environmental features
Lead Agencies/Contractors: Washington State DOT /


Category of the Issue, Problem, or Challenge
• Design
• Structural & Environmental Engineering


Summary of the Issue, Problem, or Challenge
The complex floating bridge design required mid-construction design changes due to underestimated hydrodynamic loads and environmental impact concerns. The bridge’s floating pontoons and anchorage system needed redesign to accommodate stronger currents and updated environmental regulations, causing schedule and cost impacts.


Root Cause Analysis

  • Initial hydrodynamic load calculations were overly optimistic.
  • Environmental regulations changed during construction, requiring design adaptation.
  • Late-stage design modifications lacked full integration with construction sequencing.
  • Coordination challenges between environmental consultants and design engineers.

Impacts Due to the Issue, Problem, or Challenge
• 7-month delay due to design revisions and additional environmental assessments.
• Cost overruns approximating $15 million for redesign and mitigation measures.
• Increased stakeholder scrutiny and permit review timelines.


Corrective Actions Taken

  1. Revised hydrodynamic load models using enhanced simulation tools.
  2. Integrated environmental compliance into design and construction planning.
  3. Strengthened communication channels between environmental and structural teams.
  4. Established design change management protocols to minimize disruption.

Lessons Learned

  • Complex environmental and structural design aspects must be closely coordinated.
  • Early and continuous environmental impact assessment is crucial.
  • Design changes during construction should be tightly controlled and communicated.
  • Multidisciplinary collaboration reduces risks of late-stage redesigns.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are environmental regulations fully integrated into design at the start?
  • Have hydrodynamic and other environmental loads been conservatively modeled?
  • Is there a robust design change management system during construction?
  • Are multidisciplinary teams collaborating effectively throughout the project?