Case Study: Skilled Labor Shortage Delays San Francisco Bay Bridge Retrofit (2018)
Project Overview
• Name: San Francisco–Oakland Bay Bridge East Span Seismic Retrofit
• Location: San Francisco, California
• Year: 2018
• Project Size: $6.5 billion (overall project), retrofit phase $850 million
• Scope: Seismic retrofit and replacement of eastern span, including complex cable and steel work
• Lead Agencies/Contractors: Caltrans /
Category of the Issue, Problem, or Challenge
• Skilled Labor Shortage
• Workforce Management
Summary of the Issue, Problem, or Challenge
The project experienced critical delays due to a shortage of certified structural steel welders and high-skilled ironworkers, especially those qualified for complex seismic detailing. Local labor market demand outpaced supply, limiting available crews.
Root Cause Analysis
- High regional construction activity competing for same skilled trades.
- Limited apprenticeship pipeline for specialized welding certifications.
- Insufficient contractor-led early recruitment and training programs.
- Project schedule compressed without realistic labor availability assumptions.
Impacts Due to the Issue, Problem, or Challenge
• 7-month delay in steel erection and welding activities.
• Increased labor premiums and overtime costs exceeded $5.2 million.
• Project risk profile updated to reflect workforce constraints, affecting funding allocations.
Corrective Actions Taken
- Contractor initiated targeted recruiting from other states and offered relocation incentives.
- Joint venture partners collaborated with local unions to fast-track training and certification programs.
- Caltrans adjusted schedules to allow phased steel delivery aligned with workforce availability.
Lessons Learned
- Skilled labor availability is a critical risk on high-complexity structural projects.
- Early, proactive recruitment and training partnerships mitigate labor shortages.
- Project schedules must realistically account for regional skilled labor capacity.
Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation
- Has the project team assessed skilled labor availability at preconstruction?
- Are partnerships in place to expand apprenticeship and certification pipelines?
- Is the project schedule flexible to accommodate labor supply fluctuations?