Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Ohio River Bridge Replacement
Location: Cincinnati, Ohio
Year: 2018
Project Size: $380 million
Scope: Bridge replacement including substructure and superstructure
Lead Agencies/Contractors: Ohio DOT /


Category of the Issue, Problem, or Challenge
• Subcontractor Management
• Surveying & Layout Errors


Summary of the Issue, Problem, or Challenge
The surveying subcontractor provided inaccurate alignment data, resulting in misplacement of key bridge elements and extensive rework during the construction phase.


Root Cause Analysis

  • Use of outdated surveying equipment and software.
  • Insufficient training of subcontractor field personnel.
  • Inadequate verification and cross-checking of survey data.
  • Limited oversight from prime contractor survey management.

Impacts Due to the Issue, Problem, or Challenge

  • Two-month project delay due to re-surveying and reconstruction.
  • Additional labor and material costs for correcting misalignment.
  • Disruption of construction sequencing and workflows.

Corrective Actions Taken

  1. Upgraded surveying equipment and software for accuracy.
  2. Provided additional training and certification for subcontractor staff.
  3. Established a verification protocol with redundant surveys.
  4. Increased prime contractor supervision and auditing of subcontractor data.

Lessons Learned

  • Accurate surveying is critical for infrastructure alignment and fit.
  • Technology and training investments reduce surveying errors.
  • Independent verification safeguards against costly misalignments.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are subcontractor survey teams properly equipped and trained?
  • Is survey data independently verified before construction?
  • Is prime contractor oversight adequate to catch errors early?