Project Overview
Name: Houston Buffalo Bayou Flood Control Expansion
Location: Houston, Texas
Year: 2023
Project Size: $380 million
Scope: Construction of flood barriers, pump stations, and drainage tunnels
Lead Agencies/Contractors: Harris County Flood Control District /


Category of the Issue, Problem, or Challenge
• Supply Chain Disruption
• Materials and Equipment Procurement


Summary of the Issue, Problem, or Challenge
Delays arose due to shortages and late deliveries of critical electrical components and heavy-duty pumps sourced internationally. Global semiconductor shortages and transport delays impacted availability.


Root Cause Analysis

  • Over-reliance on international suppliers for key electrical and mechanical components.
  • Underestimation of lead times during project planning.
  • Limited inventory buffer for specialized equipment.
  • Disruptions in shipping lanes and customs clearance delays.

Impacts Due to the Issue, Problem, or Challenge
• 3-month delay in pump station commissioning and system testing.
• Cost escalation due to expedited freight and substitute equipment (~$4 million).
• Disruption to coordinated scheduling of downstream civil works.


Corrective Actions Taken

  1. Developed dual sourcing strategies including domestic suppliers.
  2. Increased inventory buffers for critical electrical and mechanical items.
  3. Engaged logistics specialists to monitor and expedite customs and shipping processes.

Lessons Learned

  • Critical components sourced internationally require early procurement and risk mitigation.
  • Supply chain disruptions in tech components can ripple into heavy civil timelines.
  • Multi-sourcing and logistics expertise are key to resilience.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are critical components sourced internationally, and what are the lead times?
  • Are domestic suppliers identified and qualified as backups?
  • Is there a logistics plan to navigate customs and shipping risks?