Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: Mississippi River Bridge Replacement
Location: Vicksburg, Mississippi
Year: 2019
Project Size: $280 million
Scope: Replacement of major river bridge with deep pier foundations
Lead Agencies/Contractors: Mississippi Department of Transportation (MDOT) /


Category of the Issue, Problem, or Challenge
• Geotechnical
• Differing Site Conditions


Summary of the Issue, Problem, or Challenge
High groundwater levels and flooded soils encountered during excavation caused equipment difficulties and foundation instability, requiring redesign and additional dewatering.


Root Cause Analysis

  • Insufficient assessment of seasonal groundwater fluctuations in preliminary studies.
  • Underestimation of floodplain soil conditions.
  • Lack of real-time groundwater monitoring during construction.
  • Contract provisions did not fully allocate risks of fluctuating water conditions.

Impacts Due to the Issue, Problem, or Challenge

  • Delay of 5 months due to installation of dewatering wells and redesign of excavation support.
  • Increased costs related to pumping, equipment downtime, and soil stabilization.
  • Safety risks associated with unstable excavations and working in flooded conditions.

Corrective Actions Taken

  1. Implemented comprehensive groundwater monitoring and data collection.
  2. Designed and installed robust dewatering systems with redundancy.
  3. Revised foundation excavation methods for saturated soils.
  4. Updated contractual risk sharing related to water condition variability.

Lessons Learned

  • Groundwater and floodplain conditions must be thoroughly understood before deep excavations.
  • Real-time monitoring allows proactive management of water-related risks.
  • Clear contract language prevents disputes over water condition impacts.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are groundwater studies sufficiently detailed and ongoing?
  • Is dewatering equipment planned with capacity and redundancy?
  • Are contracts clear on water-related risks and mitigation responsibilities?