Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: KY-90 Improvement Project
Location: Pulaski County, Kentucky
Year: 2017
Project Size: $120 million
Scope: Highway embankment and roadway widening
Lead Agencies/Contractors: Kentucky Transportation Cabinet /


Category of the Issue, Problem, or Challenge
• Geotechnical
• Differing Site Conditions


Summary of the Issue, Problem, or Challenge
Construction revealed previously unknown karst voids beneath embankment area, requiring extensive ground stabilization and redesign.


Root Cause Analysis

  • Initial site investigations missed karst features due to limited geophysical survey.
  • Lack of detailed sinkhole and subsurface cavity mapping in project area.
  • Design did not anticipate high karst risk, leading to inadequate foundation preparation.

Impacts Due to the Issue, Problem, or Challenge

  • Work stopped for 5 months to perform grouting and void filling.
  • Project costs increased due to additional ground improvement measures.
  • Safety concerns for workers and future roadway users.

Corrective Actions Taken

  1. Conducted thorough geophysical surveys (electrical resistivity, ground-penetrating radar).
  2. Applied pressure grouting and compaction grouting to fill voids.
  3. Modified embankment design to include reinforced foundation layers.
  4. Implemented karst risk assessment protocols for future projects.

Lessons Learned

  • Karst terrains require specialized geophysical investigations pre-construction.
  • Designs must include contingencies for subsurface voids in karst areas.
  • Early detection prevents costly delays and safety risks.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are karst risk assessments performed early in project planning?
  • Have appropriate geophysical surveys been completed?
  • Are void mitigation and monitoring plans included?