Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Project Overview
Name: New Jersey Turnpike Widening Project
Location: Northern New Jersey
Year: 2017
Project Size: $1.2 billion
Scope: Widening of interstate highway including embankments and bridges
Lead Agencies/Contractors: New Jersey Department of Transportation (NJDOT) /


Category of the Issue, Problem, or Challenge
• Geotechnical
• Differing Site Conditions


Summary of the Issue, Problem, or Challenge
Unexpectedly soft and compressible soils were discovered during excavation, necessitating redesign of embankment foundations and additional ground improvement works.


Root Cause Analysis

  • Incomplete geotechnical site investigation and sampling prior to construction.
  • Overreliance on historical soil data without adequate exploratory borings.
  • Failure to anticipate variability in subsurface soil conditions along the corridor.
  • Insufficient contingency planning for differing site conditions.

Impacts Due to the Issue, Problem, or Challenge

  • Project delay of 6 months due to design revisions and additional ground improvement.
  • Increased costs for additional materials, equipment, and labor.
  • Impacted overall project schedule and stakeholder confidence.

Corrective Actions Taken

  1. Conducted extensive additional soil borings and testing to characterize subsurface conditions.
  2. Redesigned embankment foundations incorporating deep soil stabilization techniques.
  3. Improved pre-construction geotechnical investigation requirements for future projects.
  4. Implemented contractual provisions to address differing site conditions proactively.

Lessons Learned

  • Thorough geotechnical investigations are critical to identifying site variability.
  • Historical data should be supplemented with detailed, current site explorations.
  • Contingency planning for differing site conditions mitigates risks and delays.

Audit & Prevention: Project Control Questions to Ask on Future Projects to Help Control the Situation

  • Are comprehensive soil investigations completed before construction?
  • Is variability of subsurface conditions accounted for in design and planning?
  • Are contractual terms clear regarding differing site conditions?