Content Modules
Introduction to Heavy Civil Construction Case Studies
0/1
Cost Overrun
0/15
Project Delay
0/19
Quality Control
0/22
Differing Site Conditions
0/25
Subcontract
0/30
Project Owner
0/18
Skilled Labor
0/22
Supply Chain
0/19
Design
0/21
Project Delivery Method
0/24
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
0/35
Catalog of Over 300 Heavy Civil Construction Case Studies

Case Study: San Francisco Bay Area Steel Beam Splice Failure (2018)

Project Overview

  • Name: Bay Bridge Eastern Span Replacement
  • Location: San Francisco, California
  • Year: 2018
  • Project Size: $6.4 billion
  • Scope: Structural steel beam splicing for long-span bridge sections
  • Lead Agencies/Contractors: Caltrans /

Category of the Issue, Problem, or Challenge

  • Structural Steel
  • Welding and Bolting
  • Joint Failures

Summary of the Issue, Problem, or Challenge
A critical beam splice joint was found defective after discovery of incomplete bolt installation and weld undercuts, triggering emergency repairs and inspection of all splice joints.

Root Cause Analysis

FactorDetails
Incomplete Bolt InstallationSeveral bolts were missing or inadequately torqued.
Poor Welding QualityWeld undercuts and cracks detected at splice welds.
Lack of Final QA VerificationInsufficient post-installation inspection of splice joints.

Impacts Due to the Issue, Problem, or Challenge

  • Emergency repair work causing schedule disruption
  • Increased inspection and testing costs
  • Heightened safety risk during construction

Corrective Actions Taken

  1. Mandatory torque testing and bolt verification at all splice joints
  2. Enhanced weld procedure qualifications and welder certification checks
  3. Implementation of third-party QA inspections for all critical joints

Lessons Learned

  • Bolting and welding must be equally scrutinized in splice connections
  • Comprehensive QA inspections prevent critical joint failures
  • Proper documentation and enforcement of installation procedures are essential

Case Study: Atlanta Steel Girder Camber Adjustment Failure (2016)

Project Overview

  • Name: I-285 Perimeter Highway Widening
  • Location: Atlanta, Georgia
  • Year: 2016
  • Project Size: $350 million
  • Scope: Structural steel girder camber adjustment and erection
  • Lead Agencies/Contractors: Georgia DOT /

Category of the Issue, Problem, or Challenge

  • Structural Steel
  • Camber Correction
  • Field Adjustment

Summary of the Issue, Problem, or Challenge
Field camber adjustments on steel girders were performed without engineering oversight, resulting in over-cambering that compromised beam fit-up with deck forms.

Root Cause Analysis

FactorDetails
Lack of Engineering GuidanceAdjustments performed without structural engineer approval.
Insufficient Field MeasurementsNo verification of camber during adjustments.
Poor CommunicationDisconnection between design team and field crew.

Impacts Due to the Issue, Problem, or Challenge

  • Beam modifications and replacement requirements
  • Project delays and increased labor costs
  • Potential structural serviceability issues

Corrective Actions Taken

  1. Required engineering sign-off for all camber adjustments
  2. Use of laser measurement tools for real-time camber verification
  3. Improved field-to-design communication protocols

Lessons Learned

  • Camber modifications must be engineered and measured accurately
  • Real-time verification tools prevent costly rework
  • Coordination between field and design teams is crucial

Case Study: Miami Structural Steel Beam Corrosion Under Temporary Coating (2020)

Project Overview

  • Name: Miami Urban Expressway Expansion
  • Location: Miami, Florida
  • Year: 2020
  • Project Size: $480 million
  • Scope: Steel beam fabrication, coating, and erection
  • Lead Agencies/Contractors: Florida DOT /

Category of the Issue, Problem, or Challenge

  • Structural Steel
  • Corrosion Protection
  • Coating Failures

Summary of the Issue, Problem, or Challenge
Temporary protective coatings on steel beams failed to prevent corrosion during prolonged storage in high-humidity conditions, requiring costly recoating.

Root Cause Analysis

FactorDetails
Inadequate Temporary CoatingsCoatings were not rated for tropical humidity exposure.
Extended Storage DurationBeams stored longer than anticipated without re-coating.
Lack of MonitoringNo periodic inspection of coating condition during storage.

Impacts Due to the Issue, Problem, or Challenge

  • Increased costs for cleaning and recoating
  • Delays in beam installation schedule
  • Potential long-term durability concerns

Corrective Actions Taken

  1. Selection of coatings designed for tropical environments
  2. Scheduling and limiting storage duration for coated materials
  3. Regular inspections and maintenance of protective coatings

Lessons Learned

  • Temporary coatings must match environmental exposure
  • Storage planning must consider weather and duration
  • Monitoring is essential for corrosion protection management

Case Study: Pittsburgh Arch Rib Erection Alignment Issues (2018)

Project Overview

  • Name: Three Rivers Arch Bridge Replacement
  • Location: Pittsburgh, Pennsylvania
  • Year: 2018
  • Project Size: $400 million
  • Scope: Erection of steel arch ribs and installation of spandrel columns
  • Lead Agencies/Contractors: Pennsylvania DOT /

Category of the Issue, Problem, or Challenge

  • Structural Steel
  • Erection and Alignment
  • Arch Rib and Spandrel Columns

Summary of the Issue, Problem, or Challenge
During erection, arch ribs were found misaligned by several inches due to inadequate surveying and temporary support adjustment, causing complications in spandrel column installation.

Root Cause Analysis

FactorDetails
Insufficient SurveyingLack of frequent, precise measurement of arch rib position.
Temporary Support InstabilitySupports allowed movement during welding and bolting.
Coordination DeficienciesPoor communication between field engineers and erection crews.

Impacts Due to the Issue, Problem, or Challenge

  • Rework on alignment caused significant project delays
  • Increased labor and equipment rental costs
  • Potential impact on long-term structural performance

Corrective Actions Taken

  1. Enhanced use of laser scanning and real-time monitoring during erection
  2. Reinforced temporary support bracing to prevent movement
  3. Daily coordination meetings between surveying, engineering, and field teams

Lessons Learned

  • Continuous alignment checks critical during arch erection
  • Stable temporary supports prevent costly misalignment
  • Strong field coordination minimizes errors and delays

Case Study: Houston Spandrel Column Base Plate Corrosion (2020)

Project Overview

  • Name: Houston Inner Loop Expansion
  • Location: Houston, Texas
  • Year: 2020
  • Project Size: $380 million
  • Scope: Installation of spandrel columns and steel arch ribs
  • Lead Agencies/Contractors: Texas DOT /

Category of the Issue, Problem, or Challenge

  • Structural Steel
  • Corrosion Protection
  • Spandrel Column Base Plates

Summary of the Issue, Problem, or Challenge
Spandrel column base plates showed early-stage corrosion due to inadequate surface preparation and delayed application of protective coatings after fabrication.

Root Cause Analysis

FactorDetails
Delayed Coating ApplicationProtective coatings applied late, after exposure to weather.
Poor Surface PreparationInsufficient cleaning and rust removal before coating.
Storage ConditionsBase plates stored outdoors without shelter or protection.

Impacts Due to the Issue, Problem, or Challenge

  • Additional cost and schedule impact due to cleaning and recoating
  • Reduced durability and increased risk of long-term corrosion damage
  • Need for revised storage and handling protocols

Corrective Actions Taken

  1. Accelerated coating application immediately post-fabrication
  2. Improved surface preparation standards and inspections
  3. Revised storage procedures to protect components from weather

Lessons Learned

  • Timely application of protective coatings critical in humid climates
  • Proper surface prep essential for coating adhesion and longevity
  • Storage environment can significantly impact steel durability

Case Study: Denver Arch Rib Fabrication Weld Deficiencies (2022)

Project Overview

  • Name: Denver River Crossing Bridge
  • Location: Denver, Colorado
  • Year: 2022
  • Project Size: $350 million
  • Scope: Fabrication and erection of steel arch ribs and spandrel columns
  • Lead Agencies/Contractors: Colorado DOT /

Category of the Issue, Problem, or Challenge

  • Structural Steel
  • Welding Deficiencies
  • Fabrication

Summary of the Issue, Problem, or Challenge
Post-fabrication inspections revealed incomplete weld penetration and porosity in critical arch rib welds, requiring extensive rework before shipment to site.

Root Cause Analysis

FactorDetails
Welding Procedure DeviationWelders deviated from approved welding parameters.
Insufficient Welder TrainingSome welders lacked adequate training on complex weld joints.
Inadequate Quality InspectionsQuality control failed to detect defects early during fabrication.

Impacts Due to the Issue, Problem, or Challenge

  • Delayed shipment of steel components
  • Increased fabrication costs due to rework
  • Rescheduling of field erection activities

Corrective Actions Taken

  1. Implementation of stricter welding procedure compliance monitoring
  2. Additional welder training and certification programs
  3. Enhanced NDT inspections throughout fabrication

Lessons Learned

  • Strict enforcement of welding procedures prevents costly rework
  • Early detection of defects reduces schedule impact
  • Skilled workforce is essential for complex weld joints

Case Study: San Francisco Spandrel Column Erection Stability Issues (2017)

Project Overview

  • Name: Bay Area Arch Bridge Project
  • Location: San Francisco, California
  • Year: 2017
  • Project Size: $500 million
  • Scope: Erection of steel arch ribs and spandrel columns
  • Lead Agencies/Contractors: Caltrans /

Category of the Issue, Problem, or Challenge

  • Structural Steel
  • Erection Stability
  • Spandrel Columns

Summary of the Issue, Problem, or Challenge
During spandrel column erection, temporary supports failed to provide adequate lateral stability, resulting in minor column movement and safety concerns.

Root Cause Analysis

FactorDetails
Inadequate Temporary BracingTemporary supports were undersized for lateral load conditions.
Poor Erection Sequence PlanningErection sequence did not consider cumulative stability effects.
Lack of Field MonitoringInsufficient real-time monitoring of column movement during erection.

Impacts Due to the Issue, Problem, or Challenge

  • Halted erection activities until supports were reinforced
  • Increased labor and equipment rental costs
  • Heightened safety risk for field personnel

Corrective Actions Taken

  1. Redesigned temporary bracing with greater lateral capacity
  2. Revised erection sequence to improve structural stability during construction
  3. Installed monitoring devices to detect movement in real-time

Lessons Learned

  • Temporary supports must be designed for all load conditions, including lateral forces
  • Proper erection sequencing is critical for stability
  • Continuous field monitoring enhances safety and reduces risk

Case Study: Atlanta Arch Rib Corrosion Protection Failure (2020)

Project Overview

  • Name: Atlanta Riverfront Arch Bridge
  • Location: Atlanta, Georgia
  • Year: 2020
  • Project Size: $320 million
  • Scope: Steel arch rib fabrication and spandrel column installation
  • Lead Agencies/Contractors: Georgia DOT /

Category of the Issue, Problem, or Challenge

  • Structural Steel
  • Corrosion Protection
  • Arch Ribs and Spandrel Columns

Summary of the Issue, Problem, or Challenge
Steel arch ribs and spandrel columns exhibited early signs of rust and coating failure after prolonged exposure due to delays in installation.

Root Cause Analysis

FactorDetails
Extended On-Site StorageComponents stored outdoors without adequate protection.
Delayed InstallationConstruction schedule delays extended exposure time.
Incomplete Surface PreparationSurface contamination prior to coating application.

Impacts Due to the Issue, Problem, or Challenge

  • Need for abrasive cleaning and recoating on site
  • Additional costs and delays for rework
  • Increased risk of long-term corrosion damage

Corrective Actions Taken

  1. Improved storage protocols with covered, climate-controlled areas
  2. Accelerated installation schedule coordination to minimize exposure
  3. Implemented rigorous surface prep inspection before coating

Lessons Learned

  • Proper storage critical to preserving steel integrity
  • Scheduling should minimize time between fabrication and installation
  • Surface prep is essential for durable corrosion protection

Case Study: New York Arch Rib and Spandrel Column Dimensional Issues (2016)

Project Overview

  • Name: East River Arch Bridge Replacement
  • Location: New York City, New York
  • Year: 2016
  • Project Size: $450 million
  • Scope: Fabrication and erection of steel arch ribs and spandrel columns
  • Lead Agencies/Contractors: NYSDOT /

Category of the Issue, Problem, or Challenge

  • Structural Steel
  • Dimensional Control
  • Fabrication and Erection

Summary of the Issue, Problem, or Challenge
During assembly, several arch rib segments and spandrel columns failed to fit as designed due to dimensional inaccuracies exceeding tolerances.

Root Cause Analysis

FactorDetails
Lack of Precision in FabricationFabrication shops lacked precise measurement controls.
Insufficient Field VerificationDimensional checks before erection were inadequate.
Poor DocumentationAs-built fabrication data did not match design specifications.

Impacts Due to the Issue, Problem, or Challenge

  • Extensive field modifications and rework required
  • Project delays and cost increases
  • Compromised construction sequencing

Corrective Actions Taken

  1. Adoption of tighter fabrication quality control and measurement standards
  2. Increased use of 3D modeling and verification before shipment
  3. Enhanced field verification protocols during erection

Lessons Learned

  • Precision in fabrication critical for complex arch structures
  • Field verification essential to catch deviations early
  • Up-to-date documentation streamlines erection process

Case Study: Houston Bridge Bearing Pad Deformation (2019)

Project Overview

  • Name: Houston Bayou Bridge Replacement
  • Location: Houston, Texas
  • Year: 2019
  • Project Size: $280 million
  • Scope: Replacement of bearings and expansion joints on a multi-span bridge
  • Lead Agencies/Contractors: TxDOT /

Category of the Issue, Problem, or Challenge

  • Bridge Bearings
  • Materials Engineering
  • Structural Performance

Summary of the Issue, Problem, or Challenge
Shortly after bearing pads were installed, deformation and uneven compression were observed, leading to uneven load distribution and concerns about potential long-term damage.

Root Cause Analysis

FactorDetails
Improper Bearing SelectionBearing pads selected did not match load and movement specifications.
Installation ErrorsBearing pads were installed with misalignment and inadequate seating.
Lack of Pre-Installation InspectionInsufficient pre-installation verification of bearing surfaces.

Impacts Due to the Issue, Problem, or Challenge

  • Halted construction to reassess bearing condition
  • Additional costs for removal and replacement of bearing pads
  • Project delays due to reordering and reinstallation

Corrective Actions Taken

  1. Re-evaluation of bearing pad design parameters and material selection
  2. Implemented rigorous installation supervision and alignment checks
  3. Introduced pre-installation inspection protocol for bearing seating surfaces

Lessons Learned

  • Proper bearing selection based on accurate load and movement data is essential
  • Installation precision critical to avoid uneven stress distribution
  • Pre-installation inspections can prevent costly rework

Case Study: Seattle Expansion Joint Leakage and Seal Failure (2020)

Project Overview

  • Name: Seattle Downtown Bridge Rehabilitation
  • Location: Seattle, Washington
  • Year: 2020
  • Project Size: $190 million
  • Scope: Replacement of expansion joints and sealing systems on an aging highway bridge
  • Lead Agencies/Contractors: Washington State DOT /

Category of the Issue, Problem, or Challenge

  • Expansion Joints
  • Waterproofing and Sealant Failures

Summary of the Issue, Problem, or Challenge
Shortly after installation, expansion joints exhibited water leakage through the seals, causing corrosion to adjacent structural elements and undermining deck integrity.

Root Cause Analysis

FactorDetails
Incorrect Sealant ApplicationSealant applied outside manufacturer’s recommended conditions.
Inadequate Joint DesignJoint design did not accommodate expected thermal and traffic movements.
Insufficient Quality ControlLack of proper inspection during and after installation.

Impacts Due to the Issue, Problem, or Challenge

  • Water infiltration led to steel corrosion and concrete spalling
  • Need for premature joint replacement and repairs
  • Extended traffic disruptions and increased costs

Corrective Actions Taken

  1. Redesign of expansion joint system to meet movement and load demands
  2. Adoption of manufacturer-certified installers and strict QC procedures
  3. Periodic inspection and maintenance schedule established for joints

Lessons Learned

  • Expansion joint design must be compatible with site-specific movement profiles
  • Correct sealant application crucial to joint durability
  • Quality control during installation prevents early failures

Case Study: Chicago Bridge Bearing Seat Concrete Cracking (2018)

Project Overview

  • Name: Chicago River Bridge Replacement
  • Location: Chicago, Illinois
  • Year: 2018
  • Project Size: $400 million
  • Scope: Construction of new bearing seats and installation of elastomeric bearings
  • Lead Agencies/Contractors: Illinois DOT /

Category of the Issue, Problem, or Challenge

  • Bridge Bearings
  • Concrete Quality Control

Summary of the Issue, Problem, or Challenge
Concrete bearing seats cracked during curing and early load transfer, jeopardizing bearing stability and alignment.

Root Cause Analysis

FactorDetails
Improper Concrete Mix DesignMix had insufficient strength and was prone to shrinkage cracking.
Poor Curing ConditionsAmbient temperatures and moisture control were not adequately maintained.
Inadequate Formwork SupportFormwork movement caused stress concentrations in concrete seats.

Impacts Due to the Issue, Problem, or Challenge

  • Delays for repair and reinforcement of bearing seats
  • Increased cost for remedial measures
  • Risk of bearing misalignment and structural issues

Corrective Actions Taken

  1. Revised concrete mix to improve strength and reduce shrinkage
  2. Implemented strict curing protocols with temperature and moisture monitoring
  3. Strengthened formwork design to prevent movement during placement

Lessons Learned

  • Bearing seat concrete must meet stringent durability and strength criteria
  • Proper curing is essential to prevent early-age cracking
  • Formwork stability affects concrete quality significantly

Case Study: Miami Expansion Joint Modular Failure (2021)

Project Overview

  • Name: Miami Coastal Highway Bridge Project
  • Location: Miami, Florida
  • Year: 2021
  • Project Size: $360 million
  • Scope: Installation of modular expansion joints in a coastal bridge environment
  • Lead Agencies/Contractors: Florida DOT /

Category of the Issue, Problem, or Challenge

  • Expansion Joints
  • Modular Systems
  • Corrosion and Durability

Summary of the Issue, Problem, or Challenge
Within months of installation, modular expansion joints experienced premature wear and corrosion due to saltwater exposure, causing joint misalignment and surface roughness.

Root Cause Analysis

FactorDetails
Insufficient Corrosion ProtectionProtective coatings inadequate for marine environment.
Poor Material SelectionMaterials used were not fully resistant to saltwater corrosion.
Inadequate Maintenance PlanningLack of immediate post-installation maintenance protocols.

Impacts Due to the Issue, Problem, or Challenge

  • Increased maintenance costs and traffic interruptions
  • Early replacement of expansion joint modules required
  • Reduced overall service life and performance

Corrective Actions Taken

  1. Specification updates to require corrosion-resistant materials and coatings
  2. Enhanced maintenance and inspection schedule post-installation
  3. Use of marine-grade materials and sealants for future projects

Lessons Learned

  • Coastal and marine environments demand special materials and coatings
  • Maintenance planning must start during construction phase
  • Material selection drives longevity in harsh conditions

Case Study: Portland Bridge Elastomeric Bearing Failure (2017)

Project Overview

  • Name: Willamette River Bridge Replacement
  • Location: Portland, Oregon
  • Year: 2017
  • Project Size: $350 million
  • Scope: Replacement of elastomeric bearings on a major river crossing bridge
  • Lead Agencies/Contractors: Oregon DOT /

Category of the Issue, Problem, or Challenge

  • Bridge Bearings
  • Material Defects
  • Structural Integrity

Summary of the Issue, Problem, or Challenge
During bearing installation, several elastomeric pads exhibited premature deformation and delamination, causing uneven load transfer and alignment issues.

Root Cause Analysis

FactorDetails
Material Manufacturing DefectRubber compounds had impurities, reducing elasticity and durability.
Handling and Storage IssuesBearings were exposed to UV and extreme temperature fluctuations on site.
Insufficient QA TestingLack of batch testing before installation to catch defective units.

Impacts Due to the Issue, Problem, or Challenge

  • Suspension of bearing installation work
  • Additional procurement delays and costs to replace defective pads
  • Temporary bridge load restrictions due to uneven load distribution

Corrective Actions Taken

  1. Instituted rigorous supplier QA audits and batch testing protocols
  2. Improved on-site storage procedures to protect elastomeric materials
  3. Enhanced training for construction personnel on proper handling

Lessons Learned

  • Elastomeric bearing quality control at manufacturing stage is critical
  • Proper material storage onsite prevents premature degradation
  • Early batch testing avoids costly installation of defective components

Case Study: Atlanta Expansion Joint Concrete Deck Spalling (2018)

Project Overview

  • Name: Downtown Connector Bridge Rehab
  • Location: Atlanta, Georgia
  • Year: 2018
  • Project Size: $230 million
  • Scope: Replacement of expansion joints and deck rehabilitation on a busy urban bridge
  • Lead Agencies/Contractors: Georgia DOT /

Category of the Issue, Problem, or Challenge

  • Expansion Joints
  • Concrete Durability
  • Construction Quality

Summary of the Issue, Problem, or Challenge
Within weeks after expansion joint replacement and concrete deck pouring, significant spalling was observed adjacent to the joints, weakening the deck and exposing reinforcement.

Root Cause Analysis

FactorDetails
Poor Joint-Deck InterfaceImproper detailing led to stress concentration at joint edges.
Inadequate Concrete MixLow-quality concrete mix with insufficient air entrainment.
Improper CuringAccelerated drying caused shrinkage cracking near joints.

Impacts Due to the Issue, Problem, or Challenge

  • Early deck repairs required, impacting traffic and project schedule
  • Increased costs due to repair materials and labor
  • Risk of reinforcement corrosion and reduced deck lifespan

Corrective Actions Taken

  1. Revised joint detailing to better distribute stresses
  2. Improved concrete mix design focusing on durability and air content
  3. Implemented strict curing regime including moisture retention methods

Lessons Learned

  • Joint-deck transition areas require special attention in design and construction
  • Concrete mix design impacts durability near high-stress zones
  • Proper curing critical to prevent early-age damage

Case Study: New York Bridge Bearing Corrosion During Construction (2020)

Project Overview

  • Name: Hudson River Bridge Replacement
  • Location: New York, New York
  • Year: 2020
  • Project Size: $450 million
  • Scope: Installation of steel bridge bearings on a large river crossing
  • Lead Agencies/Contractors: NY DOT /

Category of the Issue, Problem, or Challenge

  • Bridge Bearings
  • Corrosion Protection
  • Construction Environment

Summary of the Issue, Problem, or Challenge
Steel bearings stored onsite without adequate protection began showing early signs of corrosion due to exposure to rain and humid conditions.

Root Cause Analysis

FactorDetails
Inadequate Onsite ProtectionBearings lacked protective coverings during storage.
Delayed InstallationBearings stored longer than planned due to schedule delays.
Insufficient QA ProceduresLack of regular inspection of stored components.

Impacts Due to the Issue, Problem, or Challenge

  • Costly cleaning and repainting of corroded bearings
  • Schedule impacts due to need for remediation before installation
  • Increased risk of future bearing deterioration if not properly treated

Corrective Actions Taken

  1. Established strict storage and protection protocols for steel components
  2. Implemented routine onsite inspections for corrosion
  3. Coordinated installation schedule to minimize storage times

Lessons Learned

  • Steel bearings require immediate protection upon delivery
  • Storage conditions can significantly impact component durability
  • Scheduling should consider material handling and protection needs
Index