Catalog of Over 300 Heavy Civil Construction Case Studies

About this Content
The case studies shared here are solely for educational purposes. The aim is to raise awareness of potential issues in heavy civil construction projects. The case studies are concise, and focus on five key areas: root cause, impacts, corrective measures, lessons learned, and future audit questions.
So many things can go wrong on heavy civil construction projects. Case studies focusing on failures or mistakes are essential for construction professionals to learn from past experiences, and enhance future practices.
These case studies serve as valuable educational tools for students, young professionals, and seasoned professionals. They offer real-world examples of project issues, their root causes, impacts, corrective actions, and lessons learned.
The case studies also demonstrate that to avoid repeating the same mistakes, construction professionals must have complete knowledge of the contract, and implement best practices to execute the scope of work.
The issues, problems, and challenges shown in the case studies are an indication that the best practices were not being followed. The root cause and the lessons learned tell us of the best practices that should have been in place to prevent the situations from happening.
One of the most important best practices in construction is to know the contract, follow the specifications and drawings, and when in doubt seek clarification.
A review of the case studies indicate that there are so many factor at play. However, many of the issues reported in the case studies result from interpretation of the contract specifications and drawings, planning, construction method, design flaws, coordination, and differing site conditions.
-
Master how to read and interpret contract drawings, specifications, and QC requirements to prevent contract misinterpretations and construction errors before they occur.
-
Gain in-depth knowledge of time and cost factors to consider at bid/proposal phase and construction phase to identify risks early and avoid key items from being overlooked.
-
Calculate various construction equipment production rate and have first hand knowledge of daily output before start of work, and ensure that issues related to projecting earthwork production rate are avoided on future projects.
-
Strengthen expertise in field inspection and verification items, and construction work tasks to identify risks early and stop them from escalating into costly delays or disputes.
-
Integrate thorough work planning, and cost estimating methods to ensure related problems revealed in past case studies are avoided on future projects.
-
Apply knowledge of job hazards and implement safe environment to ensure that safety incidents and accidents revealed in previous case studies are not encountered on future projects.
-
Master the use and application of trend chart for progress assessment to ensure that past cases resulting from poor project monitoring and documentation are not repeated.
- Apply daily cost analysis (per earned value analysis) and assess potential gains or losses before start of work, and allow for necessary changes to the plan to ensure that cost control problems revealed in past case studies are avoided on future projects.
What Will You Learn?
- Heavy Civil Construction Case Studies
Content Modules
Introduction to Heavy Civil Construction Case Studies
-
Introduction
Safety
-
Case Study: Oroville Dam Spillway Damage During Construction Repairs (2017)
-
Case Study: Tappan Zee Bridge Crane Collapse (New York, 2016)
-
Case Study: Big Dig Ceiling Panel Collapse (2006)
-
Case Study: I 35W Mississippi River Bridge Collapse – Minneapolis (2007)
-
Case Study: I-5 Skagit River Bridge Collapse During Construction (Washington, 2013)
-
Case Study: Tunnel Liner Segment Misalignment, Big Dig (Boston, MA, 2005)
-
Case Study: Temporary Cofferdam Failure at Chicago Riverwalk (Chicago, IL, 2017)
-
Case Study: Crane Boom Collapse at Tappan Zee Bridge Construction (New York, 2010)
-
Case Study: Landslide During Highway Construction on I-70 (Colorado, 2015)
-
Case Study: Partial Deck Collapse During I-95 Overpass Construction (Philadelphia, PA, 2014)
-
Case Study: Foundation Pile Damage During Hurricane Sandy Recovery (New York, 2012)
Cost Overrun
-
Case Study: Cost Overrun from Labor and Equipment Delays at San Francisco-Oakland Bay Bridge (San Francisco, CA, 2010)
-
Case Study: Cost Overrun Due to Unanticipated Rock Excavation at Alaskan Highway Expansion (Alaska, 2015)
-
Case Study: Cost Overrun from Material Price Escalation During Hoover Dam Bypass Construction (Nevada, 2013)
-
Case Study: Cost Overrun from Design Changes and Scope Creep on Denver RTD Rail Expansion (Denver, CO, 2017)
-
Case Study: Cost Overrun from Weather-Related Delays on I-35W Mississippi River Bridge Replacement (Minneapolis, MN, 2008)
-
Case Study: Cost Overrun from Equipment Failure on Central Arizona Project Canal Construction (Arizona, 2014)
-
Case Study: Cost Overrun from Labor Productivity Issues on Houston Ship Channel Expansion (Houston, TX, 2012)
-
Case Study: Cost Overrun from Regulatory Compliance Changes on California High-Speed Rail Segment (California, 2019)
-
Case Study: Cost Overrun from Inadequate Soil Stabilization on Louisiana Levee Construction (Louisiana, 2011)
-
Case Study: Cost Overrun from Change Orders on Seattle Alaskan Way Viaduct Replacement Tunnel (Seattle, WA, 2013)
-
Case Study: Cost Overrun from Site Access and Logistics on New Jersey Turnpike Widening (New Jersey, 2015)
-
Case Study: Cost Overrun from Inaccurate Quantity Estimations on Chicago Deep Tunnel Project (Chicago, IL, 2008)
-
Case Study: Cost Overrun from Environmental Mitigation on Portland Light Rail Expansion (Portland, OR, 2017)
-
Case Study: Cost Overrun from Material Price Escalation on Florida Highway Reconstruction (Miami, FL, 2015)
-
Case Study: Cost Overrun Due to Construction Delay on Pennsylvania Bridge Replacement (Pittsburgh, PA, 2014)
Project Delay
-
Case Study: Delay Due to Unexpected Utility Relocations on New York East River Bridge Rehabilitation (New York, NY, 2016)
-
Case Study: Delay from Adverse Weather on I-95 Reconstruction (Virginia, 2013)
-
Case Study: Delay from Regulatory Approvals on Seattle Tunnel Project (Seattle, WA, 2018)
-
Case Study: Delay from Site Conditions on Denver Airport Expansion (Denver, CO, 2015)
-
Case Study: Delay Caused by Supply Chain Disruptions on New Orleans Levee Project (New Orleans, LA, 2013)
-
Case Study: Delay Due to Equipment Failure on Texas High-Speed Rail (Dallas, TX, 2019)
-
Case Study: Delay from Design Changes on Boston Central Artery Project (Boston, MA, 2008)
-
Case Study: Delay from Permitting Issues on San Francisco Bay Bridge Retrofit (San Francisco, CA, 2012)
-
Case Study: Delay Due to Unexpected Archaeological Finds on I-70 Mountain Expansion (Colorado, 2017)
-
Case Study: Delay Due to Material Shortages on Ohio River Bridge Construction (Ohio/Kentucky, 2014)
-
Case Study: Delay Due to Inadequate Traffic Management on Houston Freeway Expansion (Houston, TX, 2016)
-
Case Study: Delay Due to Labor Shortages on I-95 Rehabilitation Project (Virginia, 2017)
-
Case Study: Delay Caused by Weather on Minneapolis Light Rail Extension (Minnesota, 2014)
-
Case Study: Delay Due to Utility Relocation Conflicts on Chicago Subway Project (Illinois, 2016)
-
Case Study: Delay from Soil Instability on Seattle Viaduct Replacement (Washington, 2015)
-
Case Study: Delay Due to Equipment Delivery on New York Subway Station Upgrade (New York, 2013)
-
Case Study: Delay from Regulatory Changes on Florida Coastal Seawall Project (Florida, 2018)
-
Case Study: Delay Due to Contractor Bankruptcy on New Jersey Tunnel Expansion (New Jersey, 2015)
-
Case Study: Delay Due to Design Changes on Dallas Flood Control Project (Texas, 2018)
Quality Control
-
Case Study: Quality Control Failures on Denver Light Rail Expansion (Colorado, 2016)
-
Case Study: Quality Control Lapses on Houston Flood Control Channel Construction (Texas, 2019)
-
Case Study: Welding Quality Control Failures on New York Harbor Bridge Construction (New York, 2014)
-
Case Study: Concrete Quality Control Failure on I-70 Reconstruction (Missouri, 2017)
-
Case Study: Insufficient QC in Steel Fabrication on Los Angeles Bridge Project (California, 2018)
-
Case Study: Quality Control Issues with Asphalt Paving on Miami Expressway Project (Florida, 2020)
-
Case Study: QC Failures in Drilled Shaft Foundations on Seattle Waterfront Project (Washington, 2019)
-
Case Study: Inadequate QC in Precast Concrete Segment Installation on Houston Tunnel Project (Texas, 2017)
-
Case Study: Quality Control Breakdown on Philadelphia Highway Reconstruction (Pennsylvania, 2021)
-
Case Study: QC Failures in Earthwork and Embankment on I-15 Expansion (Utah, 2018)
-
Case Study: QC Breakdown in Bridge Deck Waterproofing on Portland Bridge Project (Oregon, 2016)
-
Case Study: Inadequate QC in Steel Reinforcement Placement on Dallas Highway Project (Texas, 2020)
-
Case Study: QC Deficiencies in Tunnel Lining Grouting on New York Subway Extension (New York, 2019)
-
Case Study: Quality Control Failures in Pile Driving on San Francisco Bay Bridge Project (California, 2015)
-
Case Study: QC Breakdown in Shotcrete Application on Denver Light Rail Project (Colorado, 2018)
-
Case Study: QC Issues in Concrete Pouring on Miami Port Expansion (Florida, 2020)
-
Case Study: QC Failure in Asphalt Overlay on Interstate 70 Rehabilitation (Missouri, 2017)
-
Case Study: Quality Control Breakdown in Structural Steel Fabrication on Boston Tunnel Project (Massachusetts, 2018)
-
Case Study: QC Failures in Precast Concrete Panel Installation on Seattle Viaduct Replacement (Washington, 2019)
-
Case Study: Quality Control Issues in Drainage Pipe Installation on Houston Flood Mitigation Project (Texas, 2021)
-
Case Study: QC Deficiencies in Concrete Formwork on Chicago Riverwalk Extension (Illinois, 2017)
-
Case Study: Quality Control Deficiency in Dewatering Operations on Houston Subway Project (Texas, 2020)
Differing Site Conditions
-
Case Study: Unexpected Soil Conditions Causing Delay on New Jersey Turnpike Widening (New Jersey, 2017)
-
Case Study: Unforeseen Rock Layers Disrupt Foundation Excavation on Denver Light Rail Extension (Colorado, 2019)
-
Case Study: High Water Table Discovered During Excavation on San Francisco Bay Bridge Seismic Retrofit (California, 2015)
-
Case Study: Cost Overrun Due to Unforeseen Soil Conditions at Central Artery Tunnel (Boston, MA, 2003)
-
Case Study: Unanticipated Peat Layers Delay Miami Canal Expansion (Florida, 2018)
-
Case Study: Unexpected Fill Material Found Beneath Highway Embankment in Iowa (2019)
-
Case Study: Variations in Bedrock Elevation Affect Dam Foundation Excavation (Kentucky, 2020)
-
Case Study: Unexpected Sinkhole Formation Delays Roadway Construction in Louisiana (2016)
-
Case Study: Differing Site Conditions in Urban Subway Tunnel Construction Delay (New York City, 2018)
-
Case Study: Unexpected Flooded Soils Disrupt Bridge Pier Construction in Mississippi (2019)
-
Case Study: Unforeseen Glacial Till Layers Impact Highway Foundation in Minnesota (2017)
-
Case Study: Unanticipated Rock Fracturing in Tunnel Excavation Causes Delay in Pennsylvania (2018)
-
Case Study: Discovery of Contaminated Soil Causes Site Remediation and Delay in California (2019)
-
Case Study: Unexpected High Water Table Halts Tunnel Excavation in Washington State (2020)
-
Case Study: Unexpected Rock Depth Variation Delays Highway Overpass in Colorado (2018)
-
Case Study: Unforeseen Expansive Clay Delays Dam Embankment Construction in Texas (2019)
-
Case Study: Unexpected Soft Clay Layer Causes Bridge Pier Settlement in Louisiana (2016)
-
Case Study: Hidden Abandoned Mine Voids Delay Highway Project in Pennsylvania (2015)
-
Case Study: Unanticipated Frozen Ground Increases Costs in Alaska Highway Project (2017)
-
Case Study: Unexpected Fill Material Causes Retaining Wall Failure in New Jersey (2019)
-
Case Study: Unexpected Cobble and Boulder Layer Slows Foundation Work in Oregon (2018)
-
Case Study: Variable Soil Conditions Cause Bridge Abutment Settlement in North Carolina (2020)
-
Case Study: Unforeseen Underground Water Infiltration Delays Tunnel Excavation in New York (2018)
-
Case Study: Unexpected Karst Void Found During Highway Embankment Construction in Kentucky (2017)
-
Case Study: Unanticipated Layer of Organic Soils Causes Embankment Failure in Florida (2019)
Subcontract
-
Case Study: Subcontractor Safety Protocol Failure Leads to Crane Incident in Texas (2020)
-
Case Study: Subcontractor Schedule Mismanagement Causes Utility Relocation Delay in California (2019)
-
Case Study: Poor Quality Work by Subcontractor Causes Rework on Dam Spillway in Washington (2017)
-
Case Study: Subcontractor Equipment Mismanagement Causes Excavation Delays in Colorado (2019)
-
Case Study: Subcontractor Workforce Shortage Causes Pile Driving Delay in Louisiana (2018)
-
Case Study: Subcontractor Documentation Errors Delay Concrete Approval on Ohio Highway Project (2020)
-
Case Study: Subcontractor Inadequate Environmental Compliance Causes Stop-Work Order in Florida (2018)
-
Case Study: Subcontractor Delays in Asphalt Supply Chain Impact Roadway Paving Schedule in Illinois (2019)
-
Case Study: Subcontractor Electrical Installation Errors Lead to Rework on Seattle Bridge Project (2021)
-
Case Study: Subcontractor Safety Protocol Lapses Cause Work Stoppage on Texas Highway Project (2019)
-
Case Study: Subcontractor Material Quality Issues Cause Rejection of Bridge Components in New York (2020)
-
Case Study: Subcontractor Poor Scheduling Coordination Causes Concrete Pour Delays in Pennsylvania (2017)
-
Case Study: Subcontractor Inadequate Traffic Control Leads to Work Zone Accidents in Georgia (2018)
-
Case Study: Subcontractor Scheduling Conflicts Delay Drainage Installation in Colorado (2020)
-
Case Study: Subcontractor Welding Quality Issues Cause Structural Delays in Oregon (2019)
-
Case Study: Subcontractor Equipment Failure Causes Excavation Delay in Nevada (2018)
-
Case Study: Subcontractor Delay in Utility Relocation Causes Overall Project Hold-Up in New Jersey (2019)
-
Case Study: Subcontractor Inadequate Soil Testing Leads to Foundation Redesign in Michigan (2020)
-
Case Study: Subcontractor Incomplete Asphalt Testing Causes Pavement Failure in Texas (2017)
-
Case Study: Electrical Subcontractor Delays Cause Power System Installation Setbacks in California (2019)
-
Case Study: Concrete Subcontractor Quality Issues Lead to Structural Repairs in Pennsylvania (2021)
-
Case Study: Subcontractor Surveying Errors Cause Rework on Bridge Alignment in Ohio (2018)
-
Case Study: Subcontractor Delay in Steel Fabrication Impacts Bridge Construction in Washington State (2019)
-
Case Study: Subcontractor Safety Violations Delay Tunnel Excavation in Colorado (2020)
-
Case Study: Subcontractor Inadequate Traffic Control Plan Causes Worksite Shutdown in Florida (2019)
-
Case Study: Subcontractor Concrete Formwork Failure Leads to Collapse in Illinois (2020)
-
Case Study: Subcontractor Labor Disputes Cause Pile Driving Delay in Louisiana (2018)
-
Case Study: Subcontractor Poor Welding Quality Causes Structural Rework on Texas Highway Overpass (2017)
-
Case Study: Subcontractor Equipment Failure Causes Delay on California Tunnel Project (2019)
-
Case Study: Subcontractor Inadequate Concrete Mix Quality Causes Pavement Cracking in New York (2020)
Project Owner
-
Case Study: Owner-Driven Scope Creep Delays Bridge Project in Missouri (2020)
-
Case Study: Owner Delays Utility Relocation Causing Highway Project Setbacks in Colorado (2018)
-
Case Study: Owner Refuses Weather Time Extension on West Virginia Dam Project (2021)
-
Case Study: Owner Delays Environmental Permit on Coastal Highway in Oregon (2022)
-
Case Study: Delayed Owner Payments Disrupt Contractor Cash Flow on Mississippi Levee Project (2016)
-
Case Study: Owner-Mandated Redesign Halts Retaining Wall Construction in Pennsylvania (2021)
-
Case Study: Owner Non-Compliance with Historic Preservation Law Delays Bridge Project in Vermont (2020)
-
Case Study: Owner-Imposed Material Substitution Causes Structural Failures in Retaining Walls (Nevada, 2018)
-
Case Study: Delayed Owner Decision on Bridge Design Change Causes Idle Time in Kentucky (2020)
-
Case Study: Owner-Prescribed Construction Phasing Conflicts with Field Realities in Illinois (2016)
-
Case Study: Owner’s Late Right-of-Way Acquisition Delays Construction Start in Georgia (2019)
-
Case Study: Owner-Driven Scope Creep on Urban Drainage Project in Seattle (2022)
-
Case Study: Owner-Imposed Material Specification Change Halts Supply Chain in Texas (2021)
-
Case Study: Owner Funding Delays Cause Work Stoppage in California Transit Expansion (2018)
-
Case Study: Owner’s Late Design Changes on Bridge Project in Illinois (2020)
-
Case Study: Owner’s Inadequate Utility Coordination Delays Work on Phoenix LRT Expansion (2019)
-
Case Study: Owner’s Scope Creep Disrupts Dam Rehabilitation Project in Pennsylvania (2022)
-
Case Study: Owner Procurement Delays Stall Alaska Highway Project Mobilization (2017)
Skilled Labor
-
Case Study: Labor Strike Halts Seattle Tunnel Approach Construction (2016)
-
Case Study: Skilled Labor Shortage Delays San Francisco Bay Bridge Retrofit (2018)
-
Case Study: Pipefitter Labor Shortage Impacts Florida Water Treatment Plant Expansion (2019)
-
Case Study: Skilled Trades Shortage Delays Ohio River Bridge Pile Driving (2019)
-
Case Study: Delay Due to Labor Strike on California Highway Expansion (Los Angeles, CA, 2011)
-
Case Study: Cost Overrun from Labor Productivity Issues on Dallas Trinity River Project (Dallas, TX, 2012)
-
Case Study: Skilled Trades Gap Causes Delay in Colorado Hydroelectric Plant Construction (2017)
-
Case Study: Skilled Trades Shortage Hampers Chicago Transit Tunnel Expansion (2020)
-
Case Study: Skilled Electrician Shortage Delays Nevada Highway Interchange (2018)
-
Case Study: Skilled Pipefitter Shortage Delays Houston Wastewater Treatment Expansion (2021)
-
Case Study: Skilled Crane Operator Shortage Affects New York Bridge Construction (2020)
-
Case Study: Skilled Welder Shortage Impacts San Francisco Bay Bridge Retrofit (2019)
-
Case Study: Skilled Heavy Equipment Operator Shortage Delays Florida Highway Widening (2018)
-
Case Study: Skilled Concrete Finisher Shortage Delays Denver Light Rail Expansion (2022)
-
Case Study: Skilled Surveyor Shortage Causes Delay on Seattle Highway Reconstruction (2019)
-
Case Study: Skilled Electrician Shortage Hampers Chicago Transit Tunnel Upgrade (2020)
-
Case Study: Skilled Ironworker Labor Shortage Causes Delay in Dallas Bridge Construction (2018)
-
Case Study: Skilled Pipefitter Shortage Delays Houston Water Pipeline Project (2021)
-
Case Study: Skilled Asphalt Paving Crew Shortage Slows Phoenix Highway Rehabilitation (2019)
-
Case Study: Skilled Labor Shortage Delays New York Tunnel Waterproofing (2018)
-
Case Study: Skilled Carpenter Shortage Impacts San Francisco Pier Reconstruction (2019)
-
Case Study: Skilled Pipe Welder Shortage Causes Delay in Denver Water Treatment Plant Expansion (2020)
Supply Chain
-
Case Study: Supply Chain Disruptions Delay Seattle Highway Expansion (2022)
-
Case Study: Delay in Georgia Dam Rehabilitation Due to Equipment Delivery Issues (2019)
-
Case Study: Supply Chain Bottlenecks Delay Houston Flood Control Project (2023)
-
Case Study: Steel Shortages Cause Delay in Chicago Rail Overpass Project (2021)
-
Case Study: Florida Coastal Highway Project Experiences Asphalt Binder Shortage (2018)
-
Case Study: New York Tunnel Expansion Delayed by HVAC Equipment Supply Issues (2021)
-
Case Study: San Francisco Bay Bridge Retrofit Impacted by Cable Supplier Delays (2019)
-
Case Study: Seattle Light Rail Extension Faces Rebar Delivery Delays (2022)
-
Case Study: Denver Airport Expansion Delayed by Electrical Cable Shortages (2020)
-
Case Study: Houston Flood Control Project Delayed by Concrete Admixture Shortages (2023)
-
Case Study: Chicago Expressway Rehabilitation Faces Steel Plate Delivery Delays (2022)
-
Case Study: Los Angeles Highway Widening Project Impacted by Asphalt Binder Shortage (2023)
-
Case Study: Miami Port Expansion Stalled by Marine Equipment Delivery Delays (2021)
-
Case Study: New York City Subway Station Upgrade Delayed by HVAC Equipment Shortages (2022)
-
Case Study: San Francisco Bay Bridge Retrofit Hampered by High-Strength Bolt Shortages (2021)
-
Case Study: Seattle Light Rail Extension Delayed by Precast Concrete Panel Shortages (2023)
-
Case Study: Dallas Flood Control Project Halted by Pipe Delivery Disruptions (2022)
-
Case Study: Houston Highway Interchange Project Delayed by Steel Reinforcement Bar (Rebar) Shortage (2022)
-
Case Study: Chicago River Tunnel Rehabilitation Hampered by Concrete Admixture Shortages (2021)
-
Case Study: Boston Tunnel Waterproofing Project Impacted by Membrane Shortages (2022)
Design
-
Case Study: Denver I-70 Viaduct Design Flaws Cause Rework and Delay (2020)
-
Case Study: New York Subway Station Structural Design Errors Delay Completion (2019)
-
Case Study: Seattle SR 520 Floating Bridge Design Revisions Cause Construction Delays (2018)
-
Case Study: Miami Port Tunnel Design Coordination Failure Causes Structural Conflicts (2017)
-
Case Study: Cost Overrun from Design Errors on I-70 Mountain Corridor Reconstruction (Colorado, 2010)
-
Case Study: San Francisco Bay Bridge East Span Design Flaws Lead to Steel Fabrication Rework (2016)
-
Case Study: Houston Flood Control Project Design Underestimation Causes Structural Issues (2018)
-
Case Study: Minneapolis Light Rail Transit Tunnel Design Clash Causes Rework (2017)
-
Case Study: Boston Central Artery/Tunnel Project Design Revisions Delay Construction (2001)
-
Case Study: Denver FasTracks Rail Expansion Design-Construction Interface Issues (2015)
-
Case Study: Seattle Alaskan Way Viaduct Replacement Tunnel Design Adjustments (2014)
-
Case Study: Atlanta I-285/I-85 Interchange “Spaghetti Junction” Design Rework (2019)
-
Case Study: San Francisco Bay Bridge East Span Design-Construction Interface Failures (2007)
-
Case Study: Miami Port Tunnel Design Modifications Impact Schedule and Costs (2010)
-
Case Study: I-90 Floating Bridge Design Inadequacies Lead to Construction Delays (2002)
-
Case Study: Denver RTD FasTracks Design Change Impact (2013)
-
Case Study: New Orleans Flood Protection Design Flaws Revealed During Construction (2011)
-
Case Study: Seattle SR 520 Floating Bridge Design Coordination Failures (2014)
-
Case Study: Minneapolis Light Rail Transit Design-Construction Interface Issues (2011)
-
Case Study: San Francisco Central Subway Design Changes Cause Construction Delays (2015)
-
Case Study: Houston I-69 Expansion Design Conflicts Delay Construction (2018)
Project Delivery Method
-
Case Study: Los Angeles Metro Purple Line Extension – Delivery Method Challenges (2017)
-
Case Study: New Jersey Turnpike Widening – Design-Bid-Build Delivery Issues (2012)
-
Case Study: Boston Big Dig – Delivery Method Complexities and Coordination Failures (2003)
-
Case Study: Denver FasTracks Eagle P3 Project – Public-Private Partnership Delivery Challenges (2011)
-
Case Study: Seattle Alaskan Way Viaduct Replacement – Design-Build Delivery Challenges (2014)
-
Case Study: Dallas Horseshoe Project – Design-Bid-Build Delivery Limitations (2016)
-
Case Study: Houston North Houston Highway Improvement Project – Design-Build Delivery Disputes (2019)
-
Case Study: Washington D.C. 11th Street Bridge Project – Public-Private Partnership Delivery Challenges (2014)
-
Case Study: I-95 Express Lanes Extension, Miami – Design-Build Delivery Challenges (2017)
-
Case Study: San Francisco Central Subway – Design-Build Delivery Complexities (2013)
-
Case Study: New Jersey Turnpike Widening – Design-Build Delivery and Scope Management Issues (2015)
-
Case Study: Denver FasTracks Eagle P3 Project – P3 Delivery Contractual Challenges (2012)
-
Case Study: I-405 Sepulveda Pass Improvement Project – Design-Build Delivery Coordination Failures (2018)
-
Case Study: Port of Savannah Expansion – Public-Private Partnership Delivery Challenges (2016)
-
Case Study: I-70 Mountain Corridor Reconstruction – Design-Build Delivery and Environmental Risk Mismanagement (2014)
-
Case Study: Ohio River Bridges Project – Project Delivery Integration Challenges (2013)
-
Case Study: I-95 Express Lanes Expansion – Design-Build Delivery and Risk Sharing Issues (2017)
-
Case Study: Central Texas Tollway Project – P3 Delivery and Schedule Integration Failures (2019)
-
Case Study: Seattle Alaskan Way Viaduct Replacement – Design-Build Delivery and Scope Change Challenges (2015)
-
Case Study: North Carolina I-77 Express Lanes – P3 Delivery and Construction Phase Coordination Issues (2016)
-
Case Study: Los Angeles Metro Purple Line Extension – Design-Build Delivery and Interface Coordination Problems (2018)
-
Case Study: Miami Port Tunnel Project – P3 Delivery and Construction Schedule Integration Issues (2010)
-
Case Study: Denver Eagle P3 Commuter Rail Project – Delivery Method Coordination and Risk Management Failures (2016)
-
Case Study: New Jersey Turnpike Widening – Design-Bid-Build Delivery and Change Order Management Issues (2013)
Contract Changes
-
Case Study: Houston Katy Freeway Expansion – Change Order Management Failures (2012)
-
Case Study: San Francisco Bay Bridge Eastern Span Replacement – Change Order Disputes (2008)
-
Case Study: I-405 Widening Project – Change Order Cascade from Utility Relocation Delays (2015)
-
Case Study: Louisville Ohio River Bridges – Change Order Surge from Environmental Mitigation (2014)
-
Case Study: Dulles Metrorail Phase 2 – Scope Creep and Change Order Complexity (2019)
-
Case Study: I-70 Mountain Corridor (West Vail Pass) – Change Orders from Accelerated Schedule Pressures (2022)
-
Case Study: SR 99 Tunnel Project – Change Orders from Unanticipated Ground Conditions (2016)
-
Case Study: LaGuardia Airport AirTrain – Change Order Impacts from Agency Scope Shifts (2020)
-
Case Study: Central Subway Tunnel – MEP Change Orders from Incomplete Coordination (2018)
-
Case Study: I-95/I-295 Interchange – Change Orders from Stormwater System Redesign (2021)
Case Studies Grouped by the Units of the Webbook – Analyze for Relevant Preventive Audit Questions
-
Related to Earthwork Construction
-
Related to Stormwater Drainage Systems
-
Related to Base and Subbase
-
Related to Pavement
-
Related to Foundation Construction
-
Related to Retaining Wall Construction
-
Related to Concrete Construction for Heavy Civil Projects
-
Related to Structural Steel Construction
-
Related to Structural Timber Construction
Interactive Case Studies Related to Project Controls – Analyze for Corrective Project Control Measures
-
Construction Work Environment, and Knowledge of the Scope of Work
-
Administration of Submittals, and Signing of Subcontract Agreement
-
Insurance Coverages, Bonds, and Production Over Safety
-
Dispute Over Contract Changes, Stop Notice, and Contract Owner Furnished Items
-
Change Order Administration, Rework, and Union Agreement
-
Loss of Long Lead Items, Field Notification, Delayed Delivery
-
Procurement Plan, Communication, and Administration of RFI and Submittals
-
Attrition Rate, Onboarding, and Performance Issues
-
Contracting Knowledge, OSHA Citation, and Workplace Accident
-
Time on Accident-Related Issues, Certified Payroll, and Defective Contract Document
-
Inexperience, Misaligned Expectations, and Project Schedule Approval
-
Existing Underground Utilities, ADA Requirements, and Hostile Work Environment
-
Community Engagement, Field Directives, and Payment of Material Suppliers
-
Lack of Confidence, and Delayed Payment
-
Progress Payment Request, Administration of RFI and Submittal, and Roles and Responsibilities
-
Change Order Administration, Knowledge Transfer, and Project Risk Management System
-
Training of Workers, Policies and Procedures, and Motivating Workers
-
Control Budget, Good Faith Effort, and Field Visit Prior to Start of Construction
-
Supervision, and Knowledge of the Contract
-
Administration of Submittals, Agreement on Change Order, and Substituted Material
-
Inexperience, Errors and Omissions, and Removal of the Project Manager
-
False Claim, Jail Time and Workplace Accident, and Progress Measurement
-
Shop Drawings, Lay Offs, and Loss of Momentum
-
Relationships, Communication, and Getting Along
-
Documentation, Material Handling, and Timing of Request for Payment
-
Contract Drawings, Payment of Vendors, and Wrong Material Order
-
License, Inspection and Testing Budget, and Notification
-
Contract Requirements, Coordination, and Ambiguities in the Contract Documents
-
Soils Report, Timely Submittal of Contract Change Orders, and Punch List Sign Off
-
Selective Memory, Company Name Change, and Bankruptcy
-
No Where to Dump Excess Dirt, Erection of Structural Steel Columns, and Going Out of Business
-
Incorrect Safety Records, Hardly on the Jobsite, and Getting Along
-
Gas Line Clipped, and Underground Utility Marking
-
Missing Reinforcement, Field Directives, and Prequalification of Subcontractor
-
Regular Meetings, Out of Sequence Construction, and Construction Equipment Selection